2015 Sidewalk Improvement Projects

Sidewalks are an essential part of the city’s infrastructure, providing connections for pedestrians and cyclists (non-motorized). The 2015 plan is a mix of replacement of deteriorated sidewalks, which were difficult to walk on, and new sidewalks to complete important connections.

The table below lists the projects, both completed and in progress, for 2015. The city is divided into four wards, and each ward has at least one major project for the year. For more information on a specific project, please refer to the ward page.

Sidewalk Project List

Ward Street Name
From Segment
To Segment
Status
1 E. Dickson St.
N. Washington Ave.
N. Fletcher Ave.
Complete
1
S. School Ave.
W. MLK Blvd.
W. 9th St.
Complete
2 W Davidson St.
N. Park Ave.
N. College Ave.
Complete
2 N. Forest Ave.
W. Louise St.
W. Lafayette St.
Complete
2 Highland Ave.
E. Maple St.
Lafayette St.
Complete
2
N. Walnut Ave.
E. Maple St.
E. Lafayette St.
Complete
2 N. Willow Ave.
E. Maple St.
E. Lafayette St.
Complete
3 N. Applebury Dr.
Lundsford Ave.
N. Applebury Pl.
Complete
3 E. Mission Blvd.
E. Viewpoint Dr.
N. Cambridge Dr.
Complete
4 W. Markham Rd.
N. Cross Ave.
N. Palmer Ave.
Complete
wards.JPG